The Definition of DONE-DONE (taken from the old Koppsteam wiki)

Introduction

The definition of DONE-DONE in Scrum is defined as the state we want our project increments to be when we are at the end of an iteration. In effect it means things we need to do to be ready for the next delivery. Before a product backlog item can be considered done, the checklist below should be performed.

The K2 Definition of DONE-DONE

External quality

  • Source code delivers requested functionality on the TEST server. This normally means the function has been checked by the PO. This also implies a working delivery on the TEST server.
  • Application follows GUI and interaction Design guidelines. If no guideline is found for this particular thing, consider to update the Design guidelines page.
  • Acceptance tests for all user stories have been written in collaboration with the PO or at least approved by the PO afterwards. All defined tests for the story pass.

 

Internal quality

  • All production code has been pair programmed. If not, a peer review has been performed.
  • The source code follows the project coding standards, see CodingStandard.
  • There are unit tests for all new functionality.
  • Code coverage meets project standards: For newly written classes, at least 80%. For edited classes, at least 50%.
  • The configuration files and scripts (upgrade_udb.sql and others) for production have been checked and updated if needed.
  • Move fitnesse tests from "Current sprint"-page if possible.

 

Documentation

  • Any design decisions that may be relevant to a maintainer have been added to the page for design decisions, see DesignDecisions.
  • The release notes have been updated to included the added functionality or changes/fixes.
  • If the installation procedure has changed in any way, the installation guidelines must be updated